Go directly to content

Many want to be part of building the world’s first ship tunnel

A man in front of an audience
Project manager for Stad ship tunnel, Terje Skjeppestad, in front of around 160 participants at the Coastal Administration's supplier conference.
Photo:Kystverket

More than 160 representatives of design and construct contractors and suppliers attended when the Norwegian Coastal Administration organised a supplier conference on building the Stad Ship Tunnel.

“The attendance, commitment and feedback so far show that there is great interest in this project. Many potential partners are considering being part of building the world’s first ship tunnel,” says Terje Skjeppestad, project manager for Stad Ship Tunnel at the Norwegian Coastal Administration.

Preparations for the bidding competition

The Norwegian Coastal Administration is working on the basis for the competition for the construction of Stad Ship Tunnel. It is planned to announce the work as a major design and construct contract with a fixed price, which will be acquired after a competition with negotiation. It is expected to be announced after summer 2023.

The basis for the supplier conference at Gardermoen Oslo, 31.01.2023, was to prepare the contractor market for the forthcoming competition.

“There were three main objectives for the conference. Firstly, we wished to present the project by means of text, images and film and to increase awareness of the ship tunnel and the very extensive and spectacular work that will be happening out at Stadlandet. Secondly, we wished to present details of the contract, the tendering process and the technical issues etc., so as to prepare the contractor market for the forthcoming competition. Last, but not least, we are doing this to get feedback and input for our competition documents,” says Terje Skjeppestad.

A useful conference

The conference was attended by about 80 different suppliers and contractors from both Norway and abroad. In total, more than 160 people came to see and to hear about the Norwegian Coastal Administration’s work on building the world’s first ship tunnel.

“We think the attendance is absolutely fantastic. We are also pleased to note that many of the specialist subcontractors were talking to the big contractors in the mingle session after the presentations. This too was one of the aims of the conference. Many of these subcontractors have smart and useful solutions for different parts of the ship tunnel contract and it is good that these suppliers could get together with the big contractors. Together, they may be part of building Stad Ship Tunnel,” says Skjeppestad.

After the plenary session, the biggest contractors were invited to take part in one-on-one meetings with the Norwegian Coastal Administration’s project team. There will be a total of 13 such meetings in the next few days.

“We have made preliminary tendering documents available and sent out some concrete questions ahead of these meetings, so we hope and believe that the contractors are well prepared to give us some useful feedback,” says Skjeppestad.

What happens next?

“The final deadline for the contractors to give us written input to the preliminary competition documents is 15 February. After that, we will continue work on finalising the basis for tendering. The aim is to announce the competition for the design and construct contract in the third quarter of 2023 and possibly sign a contract during the third quarter of 2024,” says Skjeppestad.

The Stad Ship tunnel project

Stadhavet Sea is the most exposed and treacherous stretch of water along the Norwegian coast. The goal of the project is to ensure a safer passage through Stad.

KEY FIGURES

  • Length: 1700 metres for the tunnel run. Ca. 2200 metres from the tip of the lead construction to the tip at the other side. 
  • Height from base to ceiling: 50 metres
  • Width between the walls of the tunnel: 36 metres
  • Height from sea surface to ceiling: 33 metres
  • Cross-sectional area: 1661 m²
  • Volume of rock to be removed: Approx. 3 million m³. Equal to approx. 5,4 million m³ of blasted rock – which is equal to approx. 750 000 lorry loads.
  • Approved project budget (June 2026): NOK 8.588 billion (including VAT).
  • Estimated construction time: Approx. 5 years

CONSTRUCTION

The Norwegian Coastal Administration has awarded the design-build contract to AF Gruppen, which will be responsible for both the detailed engineering and the construction of the Stad Ship Tunnel. The contract is valued at approximately NOK 5.6 billion, excluding VAT, and is scheduled to be signed in August 2026. Construction is planned to begin in early 2027.

Boat and tunnel
At the supplier conference, the participants were able to see several new illustrations of the ship tunnel. Here from the portal area in Moldefjorden.
Photo:Kystverket / Multiconsult / LINK Arkitektur
Ship sailing out of a tunnel
Stad ship tunnel, as it may look at the tunnel opening in Kjøde.
Photo:Kystverket/Multiconsult/Link Arkitektur

Read more

Go to top